Summer/Fall 2013 Facilities Projects


Location

Project

Start Date

End Date

Athletic Complex:

Athletics - painting dugouts/press boxes

June 3, 2013

June 7, 2013

Brewer Perkins:

Install small restroom in shipping/receiving

June 3, 2013

June 21, 2013

Campus Center:

Replace old air conditioning  units throughout building (as needed)

June 3, 2013

June 7, 2013

Bowman Hall:

Decommission of biology labs for classroom use

June 4, 2013

June 7, 2013

Wellness Center:

Exterior painting - front columns

June 5, 2013

June 7, 2013

Campus Center:

2nd fl, repaint Sullivan Lounge

June 10, 2013

June 13, 2013

Campus Center:

2nd fl, Sharky's kitchen sink/new disposal needed

June 10, 2013

June 12, 2013

Facilities:

 Demolition of Ashland Street Warehouse

June 10, 2013

June 28, 2013

Venable Hall:

Roof repair

June 10, 2013

June 14, 2013

Campus Center:

2nd fl, stripping & repaint of Achievement Lounge

June 14, 2013

June 18, 2013

Campus Center:

2nd fl, acoustic panels for Sullivan Lounge; from Mill (old Sharky's panels)

June 14, 2013

June 18, 2013

 

Campus Center:

3rd fl, repaint (freshen up) CC 324A & B

June 24, 2013

June 28, 2013

Campus Center:

3rd fl, paint Susan B. Anthony Women's Center

July 1, 2013

July 3, 2013

Campus Center:

Athletics - training room addition DESIGN

July 1, 2013

Sept. 1, 2013

72 Porter Street:

Paint rooms 8 & 11

July 8, 2013

July 12, 2013

Campus Center:

Continuous rotation of "touch ups" in hallways ground level, 3rd fl

July 8, 2013

July 19, 2013

Campus Center:

3rd fl, stripping & repaint SGA suite

July 8, 2013

July 10, 2013

Facilities:

Construction of new facilities building

July 8, 2013

Sept. 30, 2013

Venable Hall:

Relocate faculty from Bowman Hall to other offices on campus

July 8, 2013

July 19, 2013

Mark Hopkins:

West entry, brick repair/repoint

July 8, 2013

July 2, 2013

72 Porter Street:

After painting is completed, build and install wooden book shelves in Room 8 & 11

July 15, 2013

July 19, 2013

Brewer Perkins:

Public Safety - repaving parking space lines for parking lot

July 15, 2013

July 13, 2013

Campus Center:

Drainage east side

July 15, 2013

July 26, 2013

 

Campus Center:

CC gym west side bleacher replacement

July 21, 2013

Aug. 9, 2013

94 Porter Street:

Exterior siding

July 22, 2013

Aug. 2, 2013

Campus Center:

Ceiling tiles evaluation (1st fl-3rd fl)

July 22, 2013

Aug. 9, 2013

Campus Center:

Bookstore ceiling, HVAC, sprinklers

July 22, 2013

Aug. 16, 2013

Mark Hopkins:

Education department (faculty office) - remove carpet and refinish wood floor

July 22, 2013

July 31, 2013

Venable Hall:

Improve/add drainage on east side/if needed

July 22, 2013

July 31, 2013

Venable Hall:

Gym floor, refinish

July 27, 2013

Aug. 9, 2013

Bowman Hall:

Classroom conversions (technology, paint, furniture)

July 29, 2013

Aug. 16, 2013

 

 

 

Facilities project list continued